Step 1-- Initiate the Process with Letter of Request to Build sent to the Bishop (2007) Step 2 -- Building & Real Estate Commission Representative Visits (2008) Step 3 -- Bishop's Preliminary Approval Letter (2008) Step 4 -- Parish Self Study approval by Diocesan Building and Real Estate Commision (2009) Step 5 -- The Finance Plan approval by Diocesan Finance Council * (2010) Town Hall Meeting #4 Update (click here) Step 6 -- Hiring of the Architect Step 7 -- First Phase, Master Site Plan & Schematics Step 8 -- Second Phase, Design Development Step 9 -- Third Phase, Construction Documents Step 10 -- Bidding, Negotiations & Contracts Step 11 -- Insurance & Bonds Step 12 -- Payments & Change Orders Step 13 -- Final Diocesan Requirements
Step 2 -- Building & Real Estate Commission Representative Visits (2008) Step 3 -- Bishop's Preliminary Approval Letter (2008) Step 4 -- Parish Self Study approval by Diocesan Building and Real Estate Commision (2009) Step 5 -- The Finance Plan approval by Diocesan Finance Council * (2010) Town Hall Meeting #4 Update (click here) Step 6 -- Hiring of the Architect Step 7 -- First Phase, Master Site Plan & Schematics Step 8 -- Second Phase, Design Development Step 9 -- Third Phase, Construction Documents Step 10 -- Bidding, Negotiations & Contracts Step 11 -- Insurance & Bonds Step 12 -- Payments & Change Orders Step 13 -- Final Diocesan Requirements
Step 3 -- Bishop's Preliminary Approval Letter (2008) Step 4 -- Parish Self Study approval by Diocesan Building and Real Estate Commision (2009) Step 5 -- The Finance Plan approval by Diocesan Finance Council * (2010) Town Hall Meeting #4 Update (click here) Step 6 -- Hiring of the Architect Step 7 -- First Phase, Master Site Plan & Schematics Step 8 -- Second Phase, Design Development Step 9 -- Third Phase, Construction Documents Step 10 -- Bidding, Negotiations & Contracts Step 11 -- Insurance & Bonds Step 12 -- Payments & Change Orders Step 13 -- Final Diocesan Requirements
Step 4 -- Parish Self Study approval by Diocesan Building and Real Estate Commision (2009) Step 5 -- The Finance Plan approval by Diocesan Finance Council * (2010) Town Hall Meeting #4 Update (click here) Step 6 -- Hiring of the Architect Step 7 -- First Phase, Master Site Plan & Schematics Step 8 -- Second Phase, Design Development Step 9 -- Third Phase, Construction Documents Step 10 -- Bidding, Negotiations & Contracts Step 11 -- Insurance & Bonds Step 12 -- Payments & Change Orders Step 13 -- Final Diocesan Requirements
Step 5 -- The Finance Plan approval by Diocesan Finance Council * (2010)
Town Hall Meeting #4 Update (click here)
Step 6 -- Hiring of the Architect
Step 7 -- First Phase, Master Site Plan & Schematics
Step 8 -- Second Phase, Design Development
Step 9 -- Third Phase, Construction Documents
Step 10 -- Bidding, Negotiations & Contracts
Step 11 -- Insurance & Bonds
Step 12 -- Payments & Change Orders
Step 13 -- Final Diocesan Requirements